Case Study Heathrow Airport

Baggage Facility

ACS Modular delivered a 120m x 40m baggage handling facility at Heathrow Terminal 5C North using modular BaggageBoX systems, enabling rapid delivery and enhanced screening capacity within a live airside environment.

Get In Touch

Project Overview

Baggage Reconciliation Facility (T5C North)

ACS Modular delivered a 120m x 40m stand-alone baggage handling facility at Heathrow Terminal 5 to support hold baggage screening operations.

The project was delivered within an exceptionally tight 21-week programme while operating in the heart of Heathrow’s live airside environment.

Get In Touch

The Challenge

Heathrow required a large-scale baggage handling facility capable of processing hold baggage while operating adjacent to active aircraft stands and passenger link bridges.

Key challenges included:

  • Construction within a live operational airside environment
  • Proximity to four Code F aircraft stands
  • Requirement for two Standard 3 baggage screening lines
  • Extremely compressed 21-week programme

The ACS Solution and Delivery

The Solution 

ACS utilised its modular BaggageBoX system, enabling baggage handling systems to be manufactured, tested and commissioned off-site. This allowed complex system integration to be completed prior to installation.

Delivery

By combining modular building systems with off-site baggage handling system integration, ACS reduced the design and manufacturing programme significantly. The facility was delivered eight days ahead of programme.

Get In Touch

Outcome

The project demonstrated a new approach to airport infrastructure delivery at Heathrow, showing how modular construction and off-site integration can accelerate delivery, reduce disruption, and improve programme certainty in a live airside environment.

Key outcomes included:

  • Major baggage screening capacity upgrade
  • Delivery within a highly compressed programme
  • Reduced cost compared with traditional construction
  • One of Heathrow’s most successful project delivery examples
Get In Touch

Key Project Facts

Facility Size

120m x 40m

Delivery

Modular BaggageBox system

Systems

2 Standard 3 hold baggage screening lines

Location

Heathrow Airport

Time Scale

21 weeks

Scope

RIBA Stage 2–6 delivery

What Our Clients Say

What I would say is that the early stakeholder engagement was really good and helped to set the project off in the right direction. The team on the ground made the day-to-day challenge of both delivering the programme and maintaining operations possible. All personnel worked as part of the wider Newquay team to provide the best possible outcome.

Sam O'DwyerNewquay Airport

Transform Your Airport Infrastructure

Let ACS build what’s next.

Partner with ACS Modular for faster, smarter delivery without compromise.
Get in touch and accelerate your project today.

Get In Touch